Guide

P28 Stages 1, 2 and 3 explained

Which stage your connection lands in decides whether P28 costs you five minutes or five thousand pounds. Here is what actually determines it.

The three stages of P28 are often described as though they were increasing levels of rigour you could opt into. They are not. They are a decision tree, and where you land is determined by your equipment and your connection point, not by how much effort you want to spend.

The practical consequence is worth stating plainly, because it is where most wasted money goes: people commission Stage 2 studies for equipment that qualified under Stage 1 all along, and people submit Stage 1 declarations for connections that were never eligible. Both are avoidable by reading the gate conditions properly.

Summary of the three P28 assessment stages
StageTriggerEffortOutcome if passed
1 LV equipment within the current and impedance thresholds Documentation only Connect without reference to the network operator
2 HV connections, or LV equipment outside Stage 1 Calculation Connect without background flicker measurement
3 Equipment that fails Stage 2 Measurement plus calculation, DNO-led Connect, on the network operator's terms

Two rules that remove the choice

Before any threshold is checked, two conditions can take Stage 1 off the table entirely. Both are easy to miss because they are not about the equipment's rating.

1. If the PCC is at HV, Stage 1 does not apply

This holds even when the equipment itself is LV. The relevant note sits with the assessment flowchart (Figure 9) and Clause 6.3.3.1 confirms it: all HV connections are assessed under Stage 2. A 400 V motor fed from your own transformer, where your point of common coupling with other customers is on the 11 kV side, is a Stage 2 problem no matter how small the motor is.

This one catches out industrial sites constantly, because the equipment looks like textbook Stage 1 equipment. The question is never "what voltage is my kit?" — it is "where is the point I share with other customers?".

2. Equipment that works as a system is assessed as a system

Clause 6.3.1 requires disturbing equipment that operates together to be treated as a single item. The two cases that come up in practice:

  • Micro-inverters forming one PV installation. Twenty inverters that each individually sit under the threshold do not give you twenty Stage 1 assessments.
  • Heat pumps with separate indoor and outdoor units. Clause 8.5 is explicit that these must be tested as one integrated system as well as individually.

The related trap

Multiple independent items at one PCC are a different question again. They do not become one system, but their combined effect may still need assessing under the summation rules in Clause 6.3.3. Clause 8.6.2 directs network operators to give special consideration to multiple EV chargers at one connection, including preventing them from switching simultaneously.

Stage 1: the simplified route

Stage 1 exists because it would be absurd to require a flicker study for a washing machine. Its logic is that if a manufacturer has already demonstrated conformance to the relevant EMC product standard, and the supply is at least as strong as the one that standard assumes, then the equipment's flicker behaviour is already known to be acceptable.

The two product standards that do the work:

  • BS EN 61000-3-3 — equipment up to 16 A per phase, tested against a reference impedance, connecting unconditionally.
  • BS EN 61000-3-11 — equipment up to 75 A per phase, connecting conditionally: the manufacturer declares the maximum supply impedance (Zmax) the equipment needs, and it is your job to show the actual supply meets it.

The four Stage 1 routes

Clause 6.3.2 sets out how equipment qualifies. There are effectively four outcomes, and it is worth identifying which one you are arguing before you gather evidence.

Route A — up to 16 A per phase, conforming to BS EN 61000-3-3

The clean case (Clause 6.3.2.1). Not subject to conditional connection. Valid provided the supply impedance at the customer's terminals does not exceed:

Stage 1 Route A maximum supply impedance
ConnectionImpedanceModulus
Single-phase 230 V (phase–neutral loop) 0.40 + j0.25 Ω 0.472 Ω
Three-phase 0.24 + j0.15 Ω 0.283 Ω

In practice this is rarely the binding constraint. The standard notes that PME (TN-C-S) LV systems typically present a supply impedance of 0.35 Ω or less, comfortably inside the single-phase figure. Services installed before about 1950 are the ones worth measuring.

Route B — up to 75 A per phase, conforming to BS EN 61000-3-3

Clause 6.3.2.2 allows connection without reference to the network operator provided the service current capacity is confirmed adequate — a check BS 7671 Regulation 132-16 requires of you anyway.

Route C — 16 to 75 A, conforming to BS EN 61000-3-11 only

This is conditional connection, and the route with the most detail. The equipment qualifies under Stage 1 only if either:

  • (a) the supply impedance at the customer's terminals — confirmed by measurement, or by calculated values the network operator provides — is no greater than the Zmax the manufacturer declares in the instruction manual; or
  • (b) both of the following:
    • the service current capacity is confirmed as at least 100 A per phase, as required by the manufacturer, and the equipment is clearly marked to that effect; and
    • the supply impedance is confirmed by measurement as no greater than the values below.
Stage 1 Route C measured impedance ceiling
ConnectionImpedanceModulus
Single-phase (phase–neutral loop, not earth-fault loop) 0.25 + j0.25 Ω 0.350 Ω
Three-phase 0.15 + j0.15 Ω 0.212 Ω

Two mistakes that invalidate a Route C claim

A 100 A fuse carrier does not establish 100 A service capacity. The carrier tells you what fits, not what the service can deliver. Capacity has to be confirmed with the network operator.

The single-phase figure is a phase–neutral loop impedance, not an earth-fault loop impedance. These are different measurements and your tester probably defaults to the wrong one. Measuring Ze and comparing it against 0.35 Ω is not the test the standard asks for.

Route D — conforming to neither product standard

Stage 1 is unavailable. The equipment may be assessed under Stage 2, though the standard itself notes that equipment failing both product standards is unlikely to meet the Stage 2 limit either. Treat this as a design problem rather than an assessment problem.

EV chargers have their own thresholds

Clause 8.6.2 sets specific figures for fixed charging equipment: up to 16 A per phase with BS EN 61000-3-3 conformance, or up to 32 A where installed at a domestic residence. The domestic 32 A allowance is what makes most home charger installations a non-event, and it is frequently missed.

What passing Stage 1 does and does not excuse

This is the subtlest part of P28 and the part most often got wrong, including — until we corrected it — by our own calculator.

The temptation is to treat the step voltage check, the RVC category check, the flicker check and the Stage 1 check as four independent tests that all have to pass. They are not. Where equipment qualifies under the EMC product-standard routes, that qualification is the demonstration of acceptable voltage-fluctuation performance. Running a separate step voltage calculation and failing the equipment on it contradicts Clause 8.6.2, which says in terms that such equipment may be connected.

The Annex A motor route is narrower, and the difference matters:

What each Stage 1 route supersedes
Qualifying route Step voltage check RVC category Stage 2 flicker
EMC product standard (Routes A–C, EV, heat pump) Superseded Superseded Superseded
Annex A motor tables Still applies Superseded Superseded

Annex A tells you a motor of that size may be started without reference to the network operator; it does not repeal the 3% step voltage limit of Clauses 5.4 and 6.2. A motor inside the Annex A table on a supply weak enough to produce more than a 3% step is still a problem, and the network operator's discretion under Clause 6.2 is the route to resolving it — not a claim that Annex A made the limit go away.

Motors: the Annex A shortcut

Annex A gives ratings for LV motors that may be connected without reference to the network operator, which for a large share of real projects is the fastest answer available. Which table applies depends on how often the motor starts and where the PCC is.

Started very frequently — intervals under one minute (Table A.1.1)

Annex A Table A.1.1
Motor typeMax output (kW)Max input (kVA)
Single-phase 230 V 0.37 1.0
Single-phase 460 V 1.50 3.0
Three-phase 400 V 2.25 4.0

PCC not at the LV busbar of a substation (Table A.1.2)

Annex A Table A.1.2
Motor typeMax output (kW)Max input (kVA)
Single-phase 230 V 0.75 1.7
Single-phase 460 V 3.00 4.5
Three-phase 400 V 4.50 6.0

PCC at the LV busbar of a substation (Table A.1.3)

The most generous case, and the one that decides most industrial motor questions. It applies to three-phase motors started at intervals of ten minutes or more, and scales with the distribution transformer:

Annex A Table A.1.3
Substation transformer (kVA)Max motor output (kW)
20022.5
300 / 31530.0
50045.0
750 / 80050.0
100075.0

Star-delta starting multiplies these ratings by 1.5 (Clause A.2). A 500 kVA substation supports a 45 kW motor direct-on-line, or a 67.5 kW motor star-delta. That factor is often the cheapest way to turn a failing assessment into a passing one.

Stage 2: calculating Pst

Stage 2 is where you stop citing product standards and start calculating. The requirement (Clause 6.3.3.2) is to establish the worst-case short-term flicker severity your equipment produces at the PCC, under worst-case supply impedance, and show that Pst ≤ 0.5.

The 0.5 figure is deliberately half the LV planning level. The headroom is what allows the network operator to accept your connection without measuring what is already on the network — if every connection stays under half, the summation of several of them still fits.

For repetitive events, the assessment usually runs through the Pst = 0.5 characteristic of Figure B.1.2, which maps how often a voltage change happens to how large it is permitted to be. The relationship is steep: a change every few seconds is held to a small fraction of a percent, while one every eight minutes or more is allowed the full 3%.

Worst case means worst case

Two things must both be pessimistic: the supply impedance (minimum plant, maximum impedance — not the value on a good day) and the operating pattern (the most frequent realistic switching, not the average). An assessment done on typical values is not a Stage 2 assessment.

Stage 3: measurement and summation

If Stage 2 does not pass, the remaining route within the standard is Stage 3, undertaken by agreement with the network operator. It differs in kind, not just in degree: instead of assuming a worst case, it measures the actual flicker background already present at the connection point, combines it with your predicted contribution using the summation rules, and compares the total against the planning level.

Stage 3 can succeed where Stage 2 fails, because Stage 2's assumption that the network is already half-loaded with flicker is frequently pessimistic. On a quiet rural network there may be far more headroom than Stage 2 credits you with.

It is also slow and expensive. It needs a flickermeter installed at the connection point for a representative period, network operator involvement throughout, and a specialist to do the summation properly. Budget weeks, not days.

Two situations push you towards Stage 3 regardless of what a simplified calculation says: several disturbing installations sharing one PCC, and RVC events frequent enough that summation between them matters. Both are outside what any single-equipment calculator, including ours, can settle.

What to do if you do not pass

A failed simplified assessment is not a refusal. It means the cheap route is closed, and there are usually four ways forward — roughly in order of what they cost.

  1. Change the starting method. Star-delta buys a factor of 1.5 under Annex A. A soft starter or a variable-speed drive effectively removes the step change altogether. Watch the consequence: a drive is a harmonic source, so you may trade a P28 problem for a G5 one.
  2. Change the connection point. Step voltage change is inversely proportional to short-circuit level, so connecting nearer the substation — or at the LV busbar rather than down a service — can move you into a different Annex A table entirely.
  3. Change the operating pattern. The permitted change grows sharply as events get less frequent. Staggering starts, or interlocking equipment so two items cannot start together, can be a control change rather than a plant change.
  4. Go to Stage 3. When the design is fixed and the numbers are marginal, measured background levels may show the headroom is there.

Where this guide stops

This is an explanation, not the standard. It paraphrases and cites; it does not reproduce P28's text, and the flowchart conditions are summarised rather than transcribed. For anything you intend to submit, work from your own copy of ENA EREC P28 Issue 2 (2019), available from the Energy Networks Association.